Three officers suspended for corruption in Patkhai reservoir

by Jeremy Spirogis
Netflix made more movies than any other studio

Raj Express The dam and canal had been authorized within the 12 months 2011-12 in village Patkhai of Sohagpur growth block of Shahdol. The value of which was eight to 9 crores, the subcontractor and the SDO, together with the contractor, fiercely did high quality work with the federal government cash, and the poor work was additionally performed. This was investigated by the crew of Water Resources Department, Jabalpur in 2017 and directed to hold out repairs and enhancements based mostly on the criticism of the farmers, however the negligent officers additionally disregarded the orders of senior officers of the division.

The farmers had been constantly complaining to the commissioner about this matter. Whose commissioner investigated Superintendent Engineer Water Resources Department Shahdol, it was revealed that the officers neither repaired nor adopted the orders of senior officers. <! –

->
                 On receiving the report, the commissioner issued a cost sheet to the then government engineer suspending the three officers.

The crew arrived from Jabalpur:

Dam and canal building work was performed in Gram Panchayat Patkhai. In which the mentioned dam and canal had been investigated by Superintending Engineer Water Resources Department, Jabalpur on complaints of high quality deterioration and canal harm. The investigation discovered the development work of dam and canal to be qualityless and the details of the criticism had been discovered to be appropriate. Even after the dam and canal building was discovered to be broken and deficiencies within the investigation, restore and enchancment work of the mentioned dam and canal has not been performed since 2017, resulting from which the crops of farmers are being broken, you’ve got made high quality and poor building work. Due to this, monetary lack of lakhs of rupees was performed.

Project damaged in two years:

The dam and canal constructed at village Patkhai was broken inside two years. Due to poor high quality of the mentioned work, farmers are being affected by irrigation facility resulting from non-maintenance of the work even after the superintending engineer instructed to do the development work. The involved officers had been instructed by the Jabalpur crew to restore and enhance them, however that too was ignored, which the farmers paid for losing their crops.

Damaged canal:

The catchment space of ​​Patkhai reservoir was disturbed, farmers couldn’t get water resulting from soil filling within the 500 meter canal. The work was not performed in keeping with technical approval. Due to which greater than two years have handed, even when Superintendent Engineer Water Resources Department Shahdol investigated the matter, he discovered that as a result of canal being broken, the farmers didn’t get water for irrigation, which broken their crops. And the officers, in violation of their obligations, did qualityless and inferior work.

Fall on these:

Two SDOs are chargeable for the development of Patkhai reservoir through which U.P. Vishwakarma Subdivisional Officer Water Resources Department Division Number-1, BNS Tiwari Sub-Divisional Officer Water Resources Department Division Number-2 and Deputy Commissioner Okay.C. The commissioner suspended Dubey water useful resource number-1 with instant impact, the then government engineer D.R. Chargesheet has additionally been issued to the figures, as a result of throughout their posting itself, no work was performed on the poor building work in addition to the restore and restore work.